Documents

User documentation

Proposal

10/16/2013 11:27 AM

Team Members:
Chris Clary
Brett Dunscomb
David Howden
Kevin Bedrossain

Project Ideas:

Idea #1: The magic eight ball. Ask the magic eight ball a yes or no question and shake. The magic eight ball will then answer your question.

Idea #2: Automatic garage door opener. Approach the door and it will sense the car and open the door.
...

Project design specifications

10/22/2013 06:00 PM

PDS for 10/23 homework

PDSrev2

10/23/2013 04:55 AM

Thanks for the great work Chris! Your document definitely got me a good start on this one. I felt like we needed a variety of musts, shoulds, and mays, and there was more that we have discussed that could be added. Not sure about the marketing requirements, but I have another version of this document with the additions I made but with the original formatting if need be.
...

Revision 2 PDS

10/23/2013 10:07 AM

I made some small changes

Weekly Progress Report

11/03/2013 12:36 AM

****Kevin******

Current week
Connected accelerometer breakout (via arduino) for initial I/O test

Next week
Confirm programing needs for accelerometer interface with cpu(via arduino)

***Brett*******

*Current Week
...

Super 8 Schematic Rev1

11/03/2013 10:27 AM

Schematic

Super 8 Schematic Rev2

11/04/2013 02:58 PM

*Named some of the important nets
*Put the correct part/footprint on schematic

Super 8 board

11/05/2013 07:56 PM

First take on the board layout.

Super 8 Schematic Rev3

11/06/2013 10:25 AM

The ERC list wasn't updating changes or something. This resulted in several non connects. The only warnings left should be with the power pins.

Super 8 board Rev 1

11/06/2013 09:58 PM

Super 8 Schematic Rev4

11/07/2013 01:56 PM

This revision addresses the comments made by the instructor. However, test points are needed before moving to the board layout. Nonetheless, there will need to be at least one more revision.

Weekly Progress Report 2

11/08/2013 09:03 PM

Kevin***

Current week

Next week

Brett****

*Current Week
Ordered Final components for project
Learned how to use AVR Dragon
Created a prototype board of Super 8 complete with accelerometer and Display and micro-controller
...

Super 8 Board Version 3

11/12/2013 06:26 PM

Current board layout and corresponding schematic. If you need to make changes to either, be sure that you open BOTH so that the changes propagate to each.

Super 8 Schematic Rev5

11/13/2013 08:44 PM

This revision addresses the result of breadboard testing of components.

Super 8 Board Rev5

11/15/2013 08:21 PM

This revision reflects the breadboard test results

Board Layout Rev 6

11/17/2013 09:55 PM

This revision reduces the overall size of the board and adds mounting holes.

Block Diagram version 1

11/19/2013 06:09 PM

This is the level-0 and level-1 block diagrams. I don't understand what he wants for the level-0 for the sub-components, that seems to be already covered by the level-1 diagram.

I need to review the Unified Modeling Language before I can add that....

Test Plan

11/26/2013 05:18 PM

Test plan document

Weekly Progress Report 3

12/11/2013 02:55 PM

Kevin
Current week
Assembled and tested board

Next week
Work on presentation

Brett
Current week
Assembled and tested board

Issues
Had to modify display code

Next week
Work on presentation

Chris
Current week
Assembled and tested board
...

Super 8 Schematic Rev6

12/11/2013 03:50 PM

Revision 6 added pull-up resistors to interrupt lines in accelerometer.

Super 8 Board Rev7

12/11/2013 03:51 PM

Revision 7 added pull-up resistors to interrupt lines in accelerometer.

Technical documentation

State Diagram Super 8

11/20/2013 12:34 AM

State Machine view

Block diagram level 0 visio revision

11/20/2013 12:54 AM

I converted and made some changes to the block diagram using visio

Block 0, Block 1, State diagram, Interaction View

11/20/2013 11:43 AM

This is a combination of the three diagrams. We just need to add our final UML.

Test planTemplate

11/26/2013 09:37 PM

This is a template for our test plan

Test plan final

11/27/2013 01:18 PM

Final test plan document